Who this checklist is for
-
Step 1 — Fix the operating point before you read the curve
-
Step 2 — Ask which design code the unit was specified against
-
Step 3 — Request the curve at your point, not the whole map
-
Step 4 — Check the surge margin, not just the surge line
-
Step 5 — Confirm shaft power at the design point and at 110%
-
Step 6 — Verify the impeller material specification
-
Step 7 — Check the seal and bearing arrangement
-
Step 8 — Confirm the FAT protocol before the contract
-
Step 9 — Get the noise guarantee in writing
-
Two things that aren't on the nine-point list
-
Common mistakes I still see
Who this checklist is for
If you're sourcing an industrial centrifugal compressor or a high-pressure centrifugal compressor for a process line, this checklist applies. It's written for the moment a quotation lands — spec sheet, performance curve, and lead time all on a few pages — and you need to decide whether it goes to engineering or goes back with questions. I run it every time. It has kept us out of three renegotiations we would have lost.
When I first started reviewing supplier submissions, I assumed the longest quotation was the most thorough. A 30-page submittal looked more professional than a 12-page one. Two years in, I realized page count proves nothing — a 12-page submittal that forces the supplier to name nine specific parameters beats a 30-page one where 28 of those pages are catalogue boilerplate. I rebuilt our enquiry template after that.
There are nine steps below. Roughly half the buyers I talk to skip four of them. I'll flag those as we go.
Step 1 — Fix the operating point before you read the curve
Every quotation should state one specific operating point: mass flow, discharge pressure, inlet temperature, inlet pressure, and gas composition. Not a range. Not "5,000–8,000 m³/h." One point.
Here's the thing: if you accept a range, you've quietly given the manufacturer permission to size the impeller for the middle of it, which may not be where you actually run. In Q3 2023 my team rejected a quotation because the "operating range" on the datasheet was 20% wider than what our process engineer had calculated. The supplier hadn't done anything wrong — they answered the question we asked. We changed the enquiry template after that one.
Check: does the quotation name a single design point, including gas composition (with water vapour fraction, if applicable)?
Step 2 — Ask which design code the unit was specified against
For oil and gas or petrochemical service, that's usually API 617. For general industrial air and gas duty, you'll see ISO 5389 or ASME PTC 10 referenced as the test code. These aren't interchangeable. A compressor built to a lighter code can still be excellent — but it will have different clearances, different bearing specs, and a different cost structure.
What most buyers don't realize is that "API 617 compliant" and "API 617 designed to" aren't always the same claim. One can be a documentation exercise. The other usually means the hardware meets the code. Ask for the reference in writing and cross-check it against the datasheet. Whether you're dealing with a centrifugal compressor manufacturer directly or through a sourcing intermediary changes who carries the cost of that cross-check.
Step 3 — Request the curve at your point, not the whole map
Most suppliers send a full performance map. That's useful for engineering, but it's not what the buying decision should rest on. Ask for a single curve segment centred on your fixed operating point, with the surge line, turndown limit, and expected efficiency at the design point all marked.
If the efficiency at your point is below what the quotation promised in the body text, you have a documentation inconsistency. This happens more often than you'd think. My records show five or six instances in 2023 alone, across maybe 40 quoted units — call it 12%, though I'd have to recheck the spreadsheet.
Step 4 — Check the surge margin, not just the surge line
The surge line shows where a centrifugal compressor stalls. The surge margin tells you how much room you have before that happens at your point. Industry practice is generally 10% minimum on flow and 5% on pressure, though the exact figure depends on the application — API 617 leans toward 10% for both in most cases. Verify the current numbers in the standard before you sign off; my copy may be out of date.
If the margin isn't stated, ask for it. If the answer is "it'll be fine," that's a flag.
Step 5 — Confirm shaft power at the design point and at 110%
This is one of the four steps most buyers skip. Quotations typically list shaft power at the design point only. But your process will occasionally push past that — start-up, trip recovery, seasonal load. Ask for shaft power at 110% of rated flow and check it against the motor rating.
When I compared our Q1 and Q4 2023 results side by side — same supplier, different enquiry templates — I finally understood why the second round came back cleaner. The template with the 110% check in it filtered out two suppliers whose motors were undersized.
Step 6 — Verify the impeller material specification
Aluminium alloy, 17-4 PH stainless, or a proprietary grade — the cost difference is real, and the service life difference depends on the gas. If the quotation says "stainless steel" without a grade, ask. If it says "aerospace-grade aluminium," ask what that means. Some suppliers use the phrase loosely.
Looking back, I should have pushed harder on the material question in our 2022 project. At the time, the datasheet was detailed enough that I assumed the grade was specified further down. It wasn't. We ended up with a 17-4 PH impeller in a service where our process engineer would have preferred 15-5 PH — not catastrophic, but a spec deviation we had to document.
Step 7 — Check the seal and bearing arrangement
For high-pressure centrifugal compressor duty, dry gas seals are the common default. For industrial centrifugal air compressor service, you'll more often see labyrinth or mechanical seals instead. Ask which is specified and why. The answer should reference your gas composition and duty cycle, not a catalogue page.
Bearings: ask whether they're tilting-pad or cylindrical. Tilting-pad is the default for larger, higher-speed units, but cylindrical bearings are cheaper and perfectly adequate for some low-speed designs. Neither is automatically right — what matters is that the answer matches the duty.
Step 8 — Confirm the FAT protocol before the contract
This is the second most-skipped step. A quotation that doesn't specify the factory acceptance test protocol is a quotation that lets the manufacturer decide what gets tested. You want to see: the test code (ASME PTC 10 for aero performance, or the relevant API reference), witness option, and the acceptance tolerance on flow, pressure, and power.
Standard ASME PTC 10 tolerance is ±4% on efficiency in most configurations, though the exact figure depends on the test class. Get the test class in writing. And confirm whether third-party witnessing is included in the quoted price or billed separately — it's usually an add-on.
Step 9 — Get the noise guarantee in writing
Noise guarantees are the third commonly skipped step. Ask for sound pressure level at 1 metre from the package, in dB(A), at the design point and at the 110% condition. Most quotations will give you an "approximate" number — that isn't a guarantee. If you're installing near a workplace, the difference between 85 dB(A) and 93 dB(A) is the difference between compliant and non-compliant.
Two things that aren't on the nine-point list
First: I should add that the quotation should state whether the anti-surge valve is in scope. It usually isn't explicit, and it's an expensive omission. Confirm it in writing.
Second: lead time is a number, not a promise. If the project depends on the date, ask for a liquidated damages clause. Most manufacturers will agree to one if the date isn't already aggressive. If they won't, that's information about their confidence in the schedule.
Common mistakes I still see
- Signing off on a range. "5,000–8,000 m³/h" sounds flexible. It isn't — it's a specification gap.
- Treating the datasheet as the contract. It's a sales document. The specification is the contract.
- Assuming zero FAT tolerance. It isn't. It's usually between 2% and 5%, depending on the code and the parameter.
- Skipping the anti-surge valve in the commercial scope. Then discovering it at commissioning.
Look, five minutes of verification beats five days of correction. The nine-point checklist I built after our third renegotiation has saved us — based on our conservative internal numbers — somewhere between $40,000 and $60,000 in avoided rework across 2023–2024. I'd have to pull the exact figure, but the order of magnitude is right.
None of this is exotic. It's just the stuff that sits between a quotation and a purchase order — which is exactly where centrifugal compressor sourcing decisions quietly go wrong.